New Facility - Construction Update 03/03/2018

This week, electrical and plumbing rough-ins were completed, the soils were backfilled and compacted, termite treatment was applied, and the slab was prepped for the upcoming concrete pour on Tuesday of next week.


transport mode of Ilc2ee Pro 2818 82/9 17:20:09

Click the link above to see a time-lapse video showing progress from the start of construction through this week.


wall neighbourhood city tree

construction

It is never too early to start advertising and creating the buzz around the new dealership! A new Porsche is prominently perched above the construction fencing for everyone passing on Savannah Hwy to admire.


construction foundation

Owners and architects toured the site this week to check on progress. (don't worry, no suits were harmed in the making of this photo)


pipeline transport construction

Once underground rough-ins were completed, the dirt was compacted and then termite treatment was applied to the soils.


soil asphalt construction

Am 11618.9 55 Am

Vapor barriers were installed to reduce moisture transfer between the soils and the concrete slab. All of the joints and the protrusions were sealed to form a continuous barrier. Finally, welded wire mesh was placed over the vapor barrier which helps unify the concrete and minimize future cracking in the slab.


Upcoming Week Look Ahead:

  • Final slab inspection
  • Slab concrete pour
  • Masonry block walls begin

Date Posted: March 3, 2018